Hello,

I am using ERPNext: v11.1.39 (master) & Frappe Framework: v11.1.36 (master)

I am testing the Auto creation of Material Request feature.

I have created an item called “Test”, and have setup the Auto Reorder as mentioned in the below image.

Also in the Stock settings have enabled the requirements for this to work as shown below.

The item “Test” had a stock of 10 quantities.

Then I created a Delivery Note for the same items with the quantity 6. After this the stock for the item got reduced to 4 quantities.

But the system has not generated the material request when the item reached below the reorder level.

So, Is there any other setting which I am missing??

Also, how much time will the system require to generate an Auto Material Request.

Please help.

Thanks & Regards,
Sujay

The system checks for stock level once at midnight and will create a Material Request if the Stock Level is lower than Re-Order Level.
If you want to manually trigger the re-order function you can use the following command
provided in the post

Auto material request is triggered via schedular, so you will see it generated around 12 PM.

Thank you so much Manan & Kenneth for the clarification. Hope this works well.

Also I would like to know what would be the status of the generated material request among these(Draft, Submitted, Pending)?