So, I have a couple of things I’m trying to figure out.
Suppose, I have a staff of 10 workers in my factory. We make different types of jewelry. I’ve entered the jewelry ITEMs into the system. I created a BOM for each ITEM and entered in OPERATIONS with time and cost into the BOM. Each item takes a different amount of time to make. My workers work 8 hours a day. For the sake of simplicity, assume that all workers can make all items and that labor cost is the same.
-
I create a work order associated with a sales order for several items. I would have 3 workers working on this work order. The time log turns out to be 2 hours with 3 workers working on this. How do I put that into the time log? Should I just multiple the time by 3 workers to get 6 hours of cost? or is there a way to associate 3 employees? or perhaps I create 3 time logs with 2 hours each?
-
Is there a way for me to create a schedule to fill the 10 workers 8 hour day with work orders. Is there a way to create a printed schedule for my workers so they know who and what they should make.
-
How do I pull a report on actual vs projected time per BOM? so that I can understand my costing better so that perhaps I need to change my BOM operation time or my costing.