Hi,
I have a scenario just want to know the outcome of that.
I have created a BOM of item X where Y, Z are Sub-Assemblies and Y1, Y2 and Z1,Z2 are respectively the components of Sub-Assembly Y and Z.
Now there is no rate defined in the system against these items.
Now if I purchase Y1,Y2,Z1,Z2 then will the system update the cost of BOM or we have to manually update the cost of BOM by pressing “Update BOM Cost” button in BOM.