Dear all,
I have this problem with Timesheet. I can reproduce every time.
- Create new TS.
- Create new entry, select project, fillout hours.
- save TS (this is important step)
- create another entry
- default project from row 1 is automatically prefilled
- change project number
- change activity type - project number is changed back to number from row 1.
This is a problem for us, because we use Project number as a starting point. Then based on project number script will filter project relevant tasks only. User can select Task. When task is selected, activity type is automatically entered. But here is the problem. After activity type is entered (and it doesn’t matter if automatically from script or manually), project number is changed to the one from row01. This creates a lot of user errors in timesheet.
Please help, if you know how can I fix this.
Screenshots below:
and gif from second entry: