Task dependencies in Projects and Project Templates

Hi

I create a project template, with the hope I’ll be able to use and customize this for a variety of projects. However I can’t see a way to create dependencies in the sequencing of tasks in the template. Whats the point of entering a task start date, when the task start date depends on the duration of depended tasks? (and given its a template, said durations won’t be known until its a real project)

Also, on the project task list screen it is tedious to create dependencies, having to go into each task, adding a row etc. This is such a basic part of project entry, can’t there be a field on the projects list if tasks table where dependencies can be entered…or maybe its there and I just don’t how to activate it?