PO link to project

Hi everyone, i find that if I click the Purchase order tag and create a new order, it cannot link to this project, but if i click the plus button beside the tag, the order will link to the project automaticly. I wonder to know why the PO cannot link in the first way

As per my understanding, when you click on the tag it only shows how many purchase order is linked with the project. You can think of it as normal list view of purchase orders with just filters applied for this project. So if you create a new PO it won’t be linked to the project. It would be created as fresh PO. To link you have to click the plus icon.

Hope this make sense.

1 Like

Thank you sir,I really appreciate for offering me explanation!:heart::heart::heart:

1 Like