Adding sub weighted tasks

Good morning,

now it’s important to add tasks in the project in order to trace the project’s progress and to link it with the financial progress and the released payments.

But I couldn’t find a way to add sub-tasks or to add a weight to each task.
because it only considers equal weight when calculating the project total progress which is not realistic at all.

I hope such a feature is included and it’s just I can’t access it. and may be some one can guide me.
otherwise hope to be added in the next coming update.
since it’s important feature.

thanks for your continous support

1 Like

Currently ERPNext does not have a feature to display project progress based on weighted tasks,it is a good suggestion.

As a work around,you can add a custom field to tasks to add weightage.

1 Like